The Chief Executive Officer of Rango Construction Limited, Dr Theodore Nsoe Adimazoya, has clarified that his company has not taken over the Bolgatanga-Bawku-Polimakom Road project from QGMI Construction UK Ltd, following reports that appeared to suggest otherwise.
The clarification follows a working visit by the Minister for Roads and Highways, Governs Kwame Agbodza, during which he expressed dissatisfaction with the state of the road and issued directives to the contractor over delays in construction.
Some subsequent media reports attributed the Minister’s warnings and directives to Rango Construction Limited, creating the impression that the company had assumed responsibility for the entire road project.
However, checks by A1 News of official project documents and records indicate that QGMI Construction UK Ltd, formerly Queiroz Galvão, remains the substantive contractor for the Bolgatanga-Bawku-Polimakom Road project.
The confusion arose following the Minister’s inspection of the deteriorated Kulaa section of the road, which had become difficult for motorists to use after the main contractor suspended work on the project.
To address the situation, Rango Construction Limited was engaged to undertake emergency remedial works on a 1.1-kilometre stretch between Bolgatanga and Zuarungu, with a two-week deadline to restore motorability.
At the time of the Minister’s visit, Rango had been on site for less than a week, undertaking the temporary intervention.
However, the Minister’s criticism of delays on the road, coupled with subsequent reports identifying Rango as the contractor responsible for the project, raised questions about whether the company had replaced QGMI.
A1 News subsequently contacted Rango Construction Limited to establish the scope of its assignment and whether it had taken over the main project.
Responding, Dr Adimazoya explained that the two companies had separate responsibilities.
“For the record, QGMI Construction UK Ltd (formerly QUEIROZ GALVAO) remains the Contractor for the Bolgatanga-Bawku-Polimakom Project road project. Rango Construction Ltd is different from QGMI Construction UK Ltd. Until the Ministry further directs, Rango’s intervention at this point remains to complete the unmotorable section of the Kulaa Bridge and QGMI will continue with the bridge itself and the remaining works of the Project,” he stated.
Dr Adimazoya emphasised that Rango’s current assignment was limited to making the deteriorated Kulaa section motorable to ease the difficulties faced by commuters.
He maintained that QGMI remained responsible for the construction of the bridge and the outstanding works on the main Bolgatanga-Bawku-Polimakom Road project, which the government has prioritised under its Big Push infrastructure programme.
Rango’s intervention is therefore a temporary measure intended to improve access along the Kulaa stretch while arrangements are made for the substantive contractor to continue work on the larger project.
David Azure | A1 Radio | Bolgatanga