Landowners and Residents of Anateem a community in the sub-district of Sumbrungu in Bolgatanga say though they are disappointed that work on the proposed Bolgatanga Airport has not begun, they are however optimistic of hosting the airport no matter the delay in starting the project.
The land was cleared in 1995 to construct a regional airport in the Upper East Region after landowners in the area leased the land to government to build the airport as a way of increasing the development potential of the region and also effectively connect one region to the other to boost socio- economic activities.
Some residents who spoke to a1radioonline.com said the project when completed would open up the community for development and help the people of the Upper East Region in the area of infrastructure, education, huge business investments, recreation, easy exportation of goods and services and other opportunities.
According to them, President John Mahama visited the site in 2014 and promised work would commence in March 2015 but that has not happened. They added that the Upper East Regional Minister Hon. James Zuugah Tiiga also visited the site in 2015.
A resident who gave his name as Daniel said many families are withholding their lands within the community in anticipation of the commencement of the construction of the airport so that they can sell to investors at good prices.
One of the landowners for the proposed site Anaa Eta said it is worrying that hundreds of shea nut trees were destroyed on that vast stretch of land in anticipation of the airport and so it would be a greater loss to the community if the project does not see the light of day after clearing several trees.
“When we gave the land out to them, they cleared a lot of trees including shea nut trees and that was a big loss to us but we did not worry because the airport is also important to us. But here is the case we have not had the airport and yet we have lost our trees. If they don’t do it then we have lost twice which would not be fair,” he said.
The runway of 60 meters width and a length of 2 kilometers were started including site clearance, excavation, provision of drains, laying of surface were part of the works until it was abandoned.
The road that was created to link the airport is currently impassible because the bridge on that stretch has collapsed.
The width of the runway was later increased to 120 meters and the length to 3.5 kilometers to meet international standards.
By: Azongo Albert | A1RADIOONLINE.com | GHANA